REWORK COST ON BUILDING PROJECTS IN THE SOUTH WESTERN PART OF NIGERIA

Main Article Content

Olatunji Ayodeji Aiyetan

Keywords

Building project, Rework, final cost, Construction process

Abstract

Right-first-time is a principle that evaluates the competence of firms, quality of product and the expertise of a professional. Rework is doing something at least one extra time due to nonconformance to requirements, could suggest the abovementioned parameter negatively either on organisation or individual. Human beings are not perfect, based on this, errors occur that may lead to rework on site and should be accommodated adequately for an uninterrupted flow of
construction activities and non-delay of delivery of projects. The south western part of Nigeria was the area of study. The quantitative and descriptive research approaches were used. The questionnaire survey and historical data were the two method used for the collection of data for the study. Simple statistical means were used for data analysis. The research findings indicate that incorrect lying of forming course, poor quality of concrete, poor plastering, and construction
errors during excavation dominate relative to areas of rework. Therefore, the study suggests that in order to eliminate or reduced drastically the occurrence of rework on future projects, consideration should be given to the following: the setting aside of a sum of money equal to the value of 0.6 – 5.0% of initial contract sum, engagement of knowledgeable foremen or having regular training of foremen, the correct construction processes should be followed in the execution of construction activities, and materials that are of good quality only should be used for constructional purposes.

Abstract 136 | PDF Downloads 121

References

Alwi, S; Hamson, K. and Mohamed, S. (1999) Investigation into the Relationship
between Rework and Site Supervision in High Rise Building Construction in
Indonesia. Process Re-engineering, Sydney, Australia. 189-195.
Ashford, J. L. (2000) The management of quality in construction. London: E&F Spon.
Barber, P., Graves, A., Hall, M., Sheath, D. And Tomkins, C. (2000) Quality Failure
costs in Civil Engineering Projects. International Journal of Quality and
Reliability Management. 17(4/5),479-92.
Kumaraswamy, M.M. and Chan, D.W.M. (1998) Contributors to Construction Delays.
Construction Management and Economics. 16. 17-29.
Construction Industry Development Agency (1995), Measuring Up or Muddling
Through: Best Practice in the Australian Non-Residential Construction Industry,
CIDA, Sydney, 59-63.
Construction Industry Institute (CII) (2001b). The field rework index: Early warning
for field rework and cost growth, Construction Industry Institute, University of
Texas at Austin, Austin, TX., Research Summary, 153-1.
Fayek, A., Dissanayake, M., & Campero, O. (2004) Developing a standard
methodology for measuring and classifying construction field rework. Canadian
Journal of Civil Engineering, 31(6), 1077-1089.
Hammarlund, Y. and Josephson, P. E. (1991) Sources of Quality Failures in
Building. Proceedings of the European symposium on Management, Quality and
Economics in Housing and other Building Sectors, Lisbon, 30 September – 4
October, 671- 9.
Love, P.E.D (2002) Auditing the Indirect Consequences of Rework in Construction:
A Case Based Approach. Managerial Auditing Journal. 17(3), 138-146.
Love, P.E.D and Li, H (2000) Quantifying the Causes and Costs of Rework in
Construction. Construction Management and Economics. 18,479-490.
Love, P.E.D. and Sohal, A.S. (2003) Capturing rework costs in projects. Managerial
Auditing Journal. 18(4), 329-39.
Palaneeswaran, E. (2006) Reducing Rework to Enhance Project performance levels.
Proceedings of the One day Seminar on ‘Recent Development in Project
Managementin Hong Kong (12May, 2006), 5.1-5.10.
Love, P.E.D., & Edwards, D.J. (2004). Determinants of rework in building
construction projects. Engineering, Construction and Architectural
Management. 11(4), 259–274.
Love, P.E.D., Irani, Z. and Edwards, D.J. (2004) A Rework Reduction Model for
Construction Projects. IEEE Trans. Eng. Manage., 51(4), 426-440.
Marosszeky, M. (2006) Performance Measurement and isual Feedback for Process
Improvements, A Special Invited Lecture Presented in the SMILE-SMC 3rd
Dessemination Workshop on 11th February, 2006, Centre for Infrastructure and
Construction Industry Development of the University of Hong Kong. Hong
Kong, 25 Slides, Available at: http://smile.hku.hk.
Zhang, D. (2009) Analysis of a Construction Small-Projects Rework Reduction
Program for a Capital Facility. A thesis presented to the University of Waterloo
Master of Applied Science in Civil Engineering. 1-131.

Similar Articles

1-10 of 199

You may also start an advanced similarity search for this article.