ANALYSIS OF CONSTRUCTION-RELATED FACTORS AFFECTING THE EFFICIENCY OF CONSTRUCTION LABOUR
Main Article Content
Keywords
Construction productivity, Construction team, Economic development, Labour efficiency, Project objectives.
Abstract
Irrespective of significant relevance of construction industry to economic growth of developed and developing nations, labour efficiency in the construction industry remains relatively low and thus affects construction project delivery and client’s satisfaction. This paper aims at exploring adverse construction related factors contributing to the shortfall of construction labour efficiency in the South African construction industry. The study adopts mixed methodological approach,
administering closed ended questionnaires to construction professionals on Western Cape and Gauteng construction sites, while experienced construction site supervisors were interviewed to validate quantitative data obtained. Statistical Package for Social Sciences (Version 22) and content analysis were used respectively to analyse data obtained. Communication ability of site managers, construction skills of site supervisors and effective site planning ability of contractors
were found as the predominant construction related factors affecting the efficiency of construction labour. This study is restricted to contractors, site supervisors and site managers’ related factors affecting the efficiency of construction labour. Adequate application of findings presented in this study will significantly reduce the current prevalent construction time and cost overruns through an improved construction workforce performance. Enhanced construction productivity is a product of construction labour efficiency that ensures achievement of construction project objectives and heightens contribution to South African economic development.
Article Metrics Graph
References
construction sites, international. Journal of construction supply chain management, Vol. 1,No. 1, pp. 56-67.
Assaf, A., and Al-Hejji, S. (2006). Causes of delay in large construction projects. International
journal of construction management, pp.349-357.
Baloyi, L., and Bekker, M. (2011). Causes of Construction cost and time overruns: The 2010 Fifa
world cup stadia in South Africa, 18(1), pp. 52-67.
Dai, J., Goodrum, M. and Malony, F. (2009). Construction Craft workers Perceptions of the factors
affecting their Productivity. Jornal of construction engineering and management, pp.217-226.
Dingsdag, P., Biggs, C., and Sheahan, L. (2008). Understanding and defining OH&S competency
for construction site positions: Workers perceptions. Journal of safety science, pp. 619-633.
Egbu, C., Ellis, R., and Gorse, C. (2004). The practice of construction management, people and
business performance. Blackwell publishing, pp. 17-150.
Enshassi, A., Mohamed, S., and Abushaban, S. (2009). Factors affecting the performance of
construction projects in the Gaza strip, Journal of civil engineering and management. 15(3), pp.269-280.
Fapohunda, A., and Stephenson P. (2010). Optimal construction resource utilization: Reflection of
site managers attribute. The pacific journal of science and technology, vol. 11, No 2, pp.353-365.
Fraser, C. (2000). The influence of personal characteristics on effectiveness of construction site
managers. Journal of construction management and economics, pp. 29-36.
Harris, F. and McCaffer, R. (2001). Modern construction management, 5th edition, Blackwell
publishing, pp. 35-95.
Harris, F. and McCaffer, R. (2013). Modern construction management, 7th edition, Blackwell
publishing, pp. 47-118.
Haseeb, M., Lu, X., Bibi, A., Dyian, M., and Rabbani, W. (2011). Problem of projects and effects
of delays in the construction industry of Pakistan. Australian journal of business and
management research, Vol. 1, No. 5, pp. 41-50.
Jarkas, M., and Bitar, G. (2012). Factors affecting construction labour productivity in Kuwait.
Journal of construction engineering and management, Vol. 138, No. 7, pp. 811-820.
Kaming, F, Olomolaiye, P., Holt, D., and Harris, C. (1997). Factors influencing craftsmen
productivity in Indonesia. Journal of project management, Vol. 15, No 1, pp. 21-30.
Kazaz, A., Manisali, E., and Ulubeyli, S. (2008). Effect of basic motivation factors on construction
workforce productivity in Turkey. Journal of civil engineering and management, 14(2), pp. 95-106.
Kines, P., Andersen, P. Spangenberg, S., Mikkelsen, L. Dyreborg, J. and Zohar, D. (2010). Journal
of safety research, pp. 399-406.
Knutson, K., Schexnayder, J., Fiori, C. and Mayo, E. (2009). Construction management
fundamentals. 2nd edition, McGraw-Hill pp. 25-50.
Levy, S. (2008). Construction superintendent operations manual. 2nd edition, McGraw-Hill pp. 3-65.
Lill, I. (2008). Sustainable management of Construction Labour: The 25th International
Symposium on automation and Robotics in Construction, pp. 864-875.
Lim, J. and Ling, Y. (2012). Human resource practices of contractors that lead to job satisfaction
of professional staff. Journal of engineering construction and architectural management, Vol.19, No. 1, pp. 101-118.
Makulsawatudom, A. Emsley, M. and Sinthawanarong, K. (2004). Critical factors influencing
construction productivity in Thailand. The Journal of KMITNB, Vol. 14, No 3, pp. 1-6.
Mincks, R. and Johnston, H. (2011). Construction jobsite management. 3rd edition, Delmar Cengage learning, pp. 115-354.
Nunnally, S. (2011). Construction method and management. 8th edition, Prentice Hall pp. 1-5.
Olander, S. (2007). Stakeholder impact analysis in construction project management. Journal of
construction management and economics, pp. 277-287.
Olomolaiye, A. and Egbu, C. (2004). The significance of Human Resource Issue in Knowledge
management within the Construction Industry- People, Problems and Possibilities. Journal of
Association of Researchers in Construction Management, vol. 1, pp. 533-540.
Palaneeswaran, E., and Kumaraswamy, M. (2001). Recent advances and proposed improvements
in contractors’ prequalification methodologies. Journal of building and environment, pp. 73-87.
Pheng, S., and Chuan, T. (2006). Environmental factors and work performance of project
managers in the construction industry. International journal of project management, pp. 24-37.
Sears, S., Sears, A. and Clouch, H. (2008). Construction project management: A practical guide to
Field construction management. 5th edition, John Wiley, pp. 14-195.
Serpell, A., and Ferrada, X. (2007). A competency-based model for construction supervisors in
developing countries. Vol. 36, No. 4, pp. 585-602.
Shohet, M., and Frydman, S. (2003). Communication patterns in construction at construction
manager level. Journal of construction engineering and management, Vol. 129, No. 5, pp.570-577.
Soham, M., and Rajiv, B. (2013).Critical Factors Affecting Labour Productivity in Construction
Projects: A case study of South Gujarat region of India. International journal of engineering
and advance technology, Vol. 2, issue 4, pp. 583-591.
Styhre, A. (2006). The bureaucratization of the project manager function: The case of the
construction industry, international journal of project management, pp. 271-276.
Styhre, A. and Josephson, P. (2006). Revisiting site manager work: stuck in the middle? Journal
of construction management and economics, pp. 521-528.
Turner, R., and Muller, R. (2004). Communication and co-operation on projects between the
project owner as principal and project manager as agent. European management journal, Vol.
11, No. 3, pp. 327-336.
Uwakweh, B. (2005). Effect of foremen on construction apprentice, journal of construction
engineering and management, Vol. 131, No. 12, pp. 1320-1327.
Walker, A. (2007). Project Management in construction, fifth edition, Blackwell
publishing, pp. 7-18.
Wong, H. (2004). Contractor performance prediction model for the United Kingdom construction
contractors: Study of logistic regression approach, journal of construction engineering and
management, Vol. 130, No. 5, pp. 691-698.
Zavadskas, K., Turskis, Z., Tamosaitiene, J., and Marina, V. (2008). Technological and economic
development of economy, Baltic journal on sustainability, pp. 462-477.