Abstract

Evidence of Professional Project Management Practices in the Ghanaian Construction Industry (GCI) dates back to the 1980s. However, to date not much  has been achieved in its advancement and deployment especially in an era where
project management is considered as an important management philosophy in achieving project success. This paper reports on a study to determine the constraints that exist in the advancement of project management practices in the GCI. The
paper adopted a two-stage data-gathering approach involving qualitative and quantitative techniques. The qualitative approach helped in identifying eighteen (18) Project Management (PM) variables that stakeholders believe are posing
challenges to effective PM practices in Ghana. Out of the eighteen variables, nine supported existing literature while the remaining nine appear to be peculiar to the Ghanaian context. Subsequently, questionnaire containing the eighteen (18)
variables were administered to 183 professionals who are involved in PM practices and then subjected to factor analysis. The paper highlights five (5) major underlying constraints namely: weak project management knowledge base, lack of clearly
defined role for project managers, poor understanding of procurement practices, weak institutional framework and poor communication practices. The paper therefore recommends that, it is important for these underlying factors to be
addressed conscientiously as they provide firm basis for advancing professional project management practices in the GCI

Abstract 238 | PDF Downloads 73

References

Albass, Y.G. & Al-Mharmah (2000) Project Management Practice by the Public
Sector in a Developing Country, International Journal of Project
Management, Practices. Vol. 10 (18):pp.105-109
Ahadzie, D. K. & Amoah-Mensah, K. (2010) Management Practices in the
Construction Ghanaian House Building Industry, Journal of Science and
Technology pp. 62-75
Ahadzie, D.K., Kissi, E. & Adjei-Kumi, T. (2012) The Status of Project
Management Practice in Ghanaian International Journal of Project
Planning and Finance Vol. 3, Num. 1, pp. 123-135
Ahadzie, D. K., Proverbs, D. G.& Sarkodie-Poku, I.(2013) Competencies
Required of Project Managers at the Design Phase of Mass House
Building Projects, International Journal of Project Management Vol.10,
pp.1-12
Anvuur, A. & Kumaraswamy, M. M. (2006) Taking Forward Public Procurement
Reforms in Ghana, CIB W107 Construction in Developing Economies
International Symposium. Construction in Developing Economies: New
Issues and Challenges Santiago, Chile, (9), pp.18-20
Amponsah, R. (2010) Improving Project Management Practice in Ghana with
Focus on Agriculture, Banking, and Construction Sectors of the Ghanaian
Economy. PHD Thesis, University of RMIT, Australia
Amoa-Mensah, K. (1999) Attaining Affordability through Cost Saving House
Building Techniques: A Case Study of Strategies That Aided Resource
Optimization in Some Affordable Housing Projects in Ghana. The
Surveyor. Newsletter of the Ghana Institution of Surveyors, pp 109-122
Amoa-Mensah, K. (2002) The Strategy of Fast Track Housing Delivery: The
Ashongman Success story, Paper presented at the Building and Road
Research Institute, Research Week Seminar, November, 1-7
Bredillet, C., Yatim, F. & Ruiz, P. (2010) Project Management Deployment: The
Role of Cultural Factors. International Journal of Project Management, 28,
pp. 183-193
BRE (2011) BRE Guidance on Construction Site Communication Available at:
http://projects.bre.co.uk/site_communications/pdf/communication
guidance.pdf [Assessed: 19th August, 2013]
Chan, D.W. M. & Kumaraswamy, M. M. (1999) Forecasting Construction
Durations for Public Housing Projects: A Hong Kong Perspective,
Building and Environment, 34, pp.633-646
Chan, W. K. L., Wang F.K.W. & Scott D. (1999) Managing Construction
Projects in China-the Transitional Period in the Millennium. International
Journal of Project Management, 17(4):pp.257–63
Chang, C.Y. & Ive, G. (2002) On the Economics Characteristics of Construction
Procurement Systems, In Procurement Systems & Technology Transfer:
CIB W92Procurement Systems Symposium, 689-710. Trinidad and
Tobago: Proceedings of the International Symposium of the Working
Commission.
Chartered Institute of Building (2002) Code of Practice for Project Management
for Construction and Development (3rd Ed.), Blackwell Publishing
Cheng, T. C. E. & Choy, P. W. C (2007), Measuring Success Factors of Quality
Management in the Shipping Industry Maritime Economics and Logistics,
Vol. 9, Issue 3, pp. 234-253
Chris, D. (2004), Statistical Methods for Organisational Research, Theory and
Practice, Routledge, Madison Ave, New York
Chung-Suk, C., and Gibson, G. E. (2001) Building Project Scope Definition
Using Project Definition Rating Index Journal of Architectural
Engineering Vol. 7, Issue: 4, pp.115-125
Crawford, L. Morris, P., Thomas, J. & Winter, M. (2006) Practitioner
Development: From Trained Technicians to Reflective Practitioners.
International Journal of Project Management 24:pp.722-733
Dib, H.Y. (2007) Visual Information Access, and Management for Life Cycle
Project Management PhD Thesis, University of Florida - M.E. Rinker
School of Building Construction
Dogbegah, K.R., Owusu-Manu D. & Omoteso K. (2011) A Principal Component
Analysis of Project Management Competencies for the Ghanaian
Construction Industry, Australasian Journal of Construction Economics
and Building, 11 (1) pp.26-40
Du, Y. M. (2001) Developing China’s Construction Supervision System Anhu
Construction Supervision; 8(1):pp.2–5
Edum-Fotwe, F.T. & McCaffer R. (2000) Developing Project Management
Competency: Perspectives from the Construction Industry .International
Journal of Project Management 111-124
Field, A. (2005a) Discovering Statistics Using SPSS for Windows, London, Sage
Publications
Field, A. (2005b), Factor Analysis Using SPSS: Theory and Application,
Available at http://www.sussex.ac.uk/users/andyf/factor.pdf [Assessed 24th
April, 2013]
Fugar, D. K. F. & Agyakwah-Baah A. B. (2010) Industry, Delay in Building
Projects in Ghana. Australasian Journal of Construction Economics and
Building11 (1/2) pp.103-116
Ghana Procurement Authority (2003) The Procurement Act 663 (2003), Accra,
Ghana (Manual of the Act)
Gibson, G. E. & Hamilton, M. R. (1994) Analysis of Pre-Project Planning Effort
and Success Variables for Capital Facility Projects, Rep. Prepared for
Construction Industry Institute, University of Texas at Austin, Austin, Tex
Goodwin, R.S. C. (1993) Skills Required of Effective Project Managers, Journal
of Management in Engineering, ASCE, 1993, Vol. 9, pp. 217-226
Gow, D. & Morss, E. (1988) The Notorious Nine: Critical problems in Project
Implementation, World Development, 16(12), pp.1399-1418
Isik, Z., Arditi, D., Dikmen, I. M. & Talat, B. M. (2009) Impact of Corporate
Strengths/Weaknesses on Project Management Competencies,
International Journal of Project Management, 27 (1), pp. 629–637
Irem, D. M., Talat, B. & Semiha, K. (2005) Strategic use of Quality
Function Deployment (QFD) in the Construction Industry Building and
Environment, Vol 40 pp. 245–255
Kartam, N., Al-Daihani T. G. & Al-Bahar J. F. (2000) Professional Project
Management Practices in Kuwait: Issues, Difficulties and
Recommendations, International Journal of Project Management; 18(2):
pp.105–109
Kikooma, J. F. (2010) Using Qualitative Data Analysis Software in a Social
Constructionist Study of Entrepreneurship, Qualitative Research Journal,
Vol. 10, No. 1, pp. 40-51
Kong, A. T. & Gray, J. (2006) Problems with Traditional Procurement in the
Malaysian Construction Industry - a Survey, In Runeson, Goran and Best,
Rick, Eds. Proceedings Australasian Universities Building Educators
Association Annual Conference, pages pp. 1-21, University of
Technology, Sydney
Koskela, L. & Howell, G., (2002) The Underlying Theory of Project Management
is Obsolete. Proceedings of the PMI Research Conference, pp. 293-302
Kreuger W.L. & Neumann W.L. (2003) Social Work Research Methods:
Qualitative and Quantitative Applications
Liu G., Qiping S., Heng Li & Liyin S. (2004) Factors Constraining the
Development of Professional Project Management in China’s Construction
Industry. International Journal of Project Management 22, pp.203–211
Loo, R. (2002) Working towards Best Practices in Project Management: A
Canadian Study, International Journal of Project Management, 20:pp.93-
98
Masterman, J. W. E. (1992) An Introduction to Building Procurement Systems
2nd edn, London: E & FN Spon.
Masterman, J. W. E. (2002) An introduction to Building Procurement Systems
2nd edn. London: E & FN Spon
Ministry of Finance and Economic Planning, (2005) Annual Report, Available at
http://www.mofep.gov.gh/?q=search/node/2003%20financial%20report[A
ccessed 8th February, 2013]
Morris, P. W.G. (1997) Why IT Projects Fail. In: Earl, M, (ed.) IT Management,
Oxford University Press.
Murray, M. D. & Langford, D A (1998) Construction Procurement Systems: A
Linkage with Project Organizational Models, In: Hughes, W (Ed.), 14th
Annual ARCOM Conference, 9-11.University of Reading. Association of
Researchers in Construction Management, Vol. 2, 544-52
Norusis, M. (1988) The SPSS guide to data analysis for SPSS-X, Chicago, SPSS
Inc
Odusami, K.T., Iyagba, R.R.O., & Onirin, M. M. (2003) The Relationship between
Project Leadership, Team Cooperation and Construction Project,
International Journal of Project Management, Vol. 21, pp. 519 –527.
Omidvar, G., Samad, Z., & Zafarghandi, S. (2011). Critical Evaluation of Project
Manager’s Competency Standards for Proposing a Comprehensive Model.
In: Proceedings of the 1er Congrès International en Management et
Gestion des projets. Gatineau, (Québec), Canada, 2011, 1–26
Rwelamila, P.D. (2004) Project Planning, Scheduling and Control: Study Guide
for MBLEPM-Y. South Africa: University of South Africa
Shenhar, A. J. (1998) From Theory to Practice: Toward a Typology of Project
Management Styles, IEEE Transactions on Engineering Management, Vol.
45, No. 1, pp. 33-48
Turner, J. R. (1999) Project Management: A Profession Based on Knowledge or
Faith? International Journal of Project Management, Vol. 17, No. 6, pp.
329-330
Walker, A. (2002) Project Management in Construction- Fourth Edition.
Blackwell Science Limited. Blackwell Publishing Company. Oxford.
Walter, S. (2011) CAQDAS and Qualitative Syllogism Logic—NVivo 8 and
MAXQDA 10 Compared [91 paragraphs]. Forum Qualitative
Sozialforschung/Forum: Qualitative Social Research, 12(1), Art. 21,
http://nbn-resolving.de/urn:nbn:de:0114-fqs1101218 [8th February, 2014]
White, D. and J. Fortune (2002) Current Practice in Project Management – An
Empirical Study, International Journal of Project Management 20: 1-11
Winch, G.M (1997) Thirty Years of Project Management: What have we
Learned? Paper Presented at the British Academy of Management
Conference, Aston University, Birmingham
Wresting, G. (1997). Ghana Public Procurement Re-Form, An Audit Report
Prepared for the World Bank, Stokholm: Advokatfiriman Cederquist KB.
World Bank (1996) Ghana 1996 Country Procurement Assessment Report,
Washington, D.C.: The World Bank
World Bank (2003) Ghana 2003 Country Procurement Assessment Report,
Washington: Ghana Country Department: The World Bank

Similar Articles

11-20 of 214

You may also start an advanced similarity search for this article.