DETERMINING THE EFFECTIVENESS OF CONCURRENT ENGINEERING THROUGH THE ANALYTICAL HIERARCHY PROCESSING OF PROJECT SUCCESS CRITERIA

Main Article Content

N.A Aniekwu
A.C. Igboanugo
M.K. Onifade

Keywords

Project Success Criteria, Project Delivery Method, Analytical Hierarchy Process, Eigen-vectors.

Abstract

The emergence of Concurrent Engineering (CE) as the Project Procurement method of choice for effective integration and coordination into construction has been gaining grounds. However, this is based mainly on empirical data that were derived majorly from the implementation of CE within the manufacturing environment. Thus the theoretical foundations of CE has been more empirical that statistical. Although science is driven by data, strong theoretical foundations must exist in order to explain that data. This work seeks to confirm statistically, the prominence of concurrent engineering as the method which offers the most scope for effective attainment of construction objectives of Cost, Time, Quality and Clients
Satisfaction. Using the Analytical Hierarchy Process (AHP) model, these project success criteria were used as the primary criteria, along with its sub-criteria, to calculate the Eigenvectors, in order to synthesize a pair-wise comparison matrix of the criteria. Thus the priority weight vectors were obtained and used for the ranking of the four principal construction delivery methods: Traditional method, the Design and Build method, the Programme management method and the Concurrent Engineering method. The results of the data computations gave a ranking of the four (4) principal project delivery methods of; Traditional sequential delivery, Programme management, Design and build and CE, with the values 0.0001, 0.1027, 0.2062 and 0.6910 respectively. CE ranked highest in its effectiveness in attaining construction goals. The work thus confirm statistically, the prominence of concurrent engineering as the method which offers the most scope for effective  attainment of construction objectives of Cost, Time, Quality and Clients Satisfaction.

Abstract 44 | PDF Downloads 11

References

Anagnostopoulos, K. P, Vavatsikos A. P. (2006). An AHP Model for Construction Contractor
Prequalification. An International Journal of Operational Research. Vol. 6, No.3 / September -
December 2006
Aouad, G.; Cooper, R.; Kagioglou, M.; Hinks, J. and Sexton, M. (1998). A Synchronised
Process/IT Model to support the co-maturation of processes and it in the Construction
sector, Time Research Institute, University of Salford.
Ballantine, J, Bonner, M, Levy, M, Martin, A, Munro, I and Powell, PL, (1996). The 3-D model
of information systems successes: the search for the dependent variable continues.
Information Resources Management Journal, 1996, 9(4), 5±14.
Banwell, H. (1964). Report of the Committee on the placing and Management of Contracts for
Building and Civil Engineering work; H.M.S.O.
Carter, D. E. (1994). Concurrent Engineering, Proceedings of the 2nd. International Conference
on Concurrent Engineering and Electronic Design Automation (CEEDA ‘94), 7–8
April, pp. 5–7.
Constable, G. (1994). Concurrent Engineering – its Procedures and Pitfalls, Measurement and
Control, Vol. 27, No. 8, pp. 245–247.
de Wit, A, (1988). Measurement of project management success. International Journal of
Project Management, 1988, 6(3), 164± 170.
Dowlatshahi, S. (1994). A Comparison of Approaches to Concurrent Engineering’,
International Journal of Advanced Manufacturing Technology, Vol. 9, pp. 106–113.
Emad Elbeltagi, (2009). Lecture Notes on Construction project management, Structural
Engineering Department, Mansoura University, Egypt. 2009.
Evbuomwan, N. F. O., Sivaloganathan, S. and Jebb, A. (1994). A State of the Art Report on
Concurrent Engineering, in Paul, A. J. and Sobolewski, M. (eds), Proceedings of
Concurrent Engineering: Research and Applications, 1994 Conference, 29–31 August,
Pittsburg, Pennsylvania, pp. 35–44.
Forman E.H. and Selly M.A. (2002). Decision by objectives. World Scientific Publications.
Frank, D. N. (1994). Concurrent Engineering. A Building Block for TQM’, Annual
International Conference Proceedings – American Production and Inventory Control
Society (APICS), Falls Church, VA, USA, pp. 132–134.
Latham, M. Sir (1993). Trusting the Team; HMSO.
Latham, M. Sir (1994). Constructing the Team. Joint review of procurement and contractual
arrangements in the UK construction industry. Department of the Environment, UK.
1994.
Madan, P. (1993). Concurrent Engineering and its Application in Turnkey Projects
Management, IEEE International Management Conference, pp. 7–17.
McCoy FA. (1987). Measuring Success: Establishing and Maintaining A Baseline, Project
management Institute Seminar/Symposiun Montreal Canada, Sep. 1987, 47±52.
Morris P.W.G. and Hough, G.H. (1987). The Anatomy of Major Projects. John Wiley, 1987.
Nicholas, J. M. (1994), ‘Concurrent Engineering: Overcoming Obstacles to Teamwork’,
Production and Inventory Management, Vol. 35, No. 3, pp. 18–22.
Oilsen, R.P, (1971). Can project management be defined? Project Management Quarterly,
1971, 2(1), 12±14.
Pinto, J.K and Slevin, D.P, (1988). Critical success factors across the project lifecycle. Project
Management Journal, 1988, XIX, 67± 75.
Prasad, B. (1996), Concurrent Engineering Fundamentals, Volume 1: Integrated Products and
Process Organization, Prentice Hall PTR, NJ.
Saarinen, T, (1990). Systems development methodology and project success. Information and
Management, 1990, 19, 183±193.
Saaty, T.L, (1980). The Analytic Hierarchy Process, McGraw-Hill, New York, NY.
Saaty T.L. (1990). How to make a decision: The Analytic Hierarchy Process. European Journal
of Operational Research, 48, 9-26.
Saaty, T.L, (1994). Fundamentals of Decision Making and Priority Theory with the Analytic
Hierarchy Process, RWS Publications, Pittsburgh, PA.
Saaty T.L. and Vargas L.G. (1994). Decision making with the Analytic Hierarchy Process. RWS
Publications.
Saaty T.L. (1995). Decision making for leaders, 3rd Edition. RWS Publications.
Smith, J., Tomasek, R., Jin, M. G. and Wang, P. K. U. (1995). Integrated System Simulation,
Printed Circuit Design, Vol. 12, No. 2, pp. 19–20, 22, 63.
Taylor III, Bernard W. (2002). Management Science, (seven edition) New Jersey: Pearson
Prentice-Hall, Inc.
Thamhain, H. J. (1994). Concurrent Engineering: Criteria for Effective Implementation’,
Industrial Management, Vol. 36, No. 6, pp. 29–32.
Turner J. R. (1993). The Handbook of Project-based Management. McGraw-Hill, 1993.
Vargas L.G. (1990). An overview of the Analytic Hierarchy Process and its
applications. European Journal of Operational Research, 48(1), 2-8.
Wateridge, J, (1989). How can IS/IT projects be measured for success? International Journal
of project Management, 1998, 16(1), 59± 63.
Westerveld E. (2003). The Project Excellence Model®: linking success criteria and critical
success factors. International Journal of Project Management, 2003, vol. 21. pg 412
Winston, Wayne L. & Albright, S. Christian. Practical Management Science. Spreadsheet
Modelling and Applications. Duxbury Press, 1997 pp
Yogeswaran, K, Kumaraswamy, MM and Miller, DRA (1997). Perceived sources and causes
of construction claims. Journal of Construction Procurement, 3(3), pp.3-26.

Similar Articles

1-10 of 158

You may also start an advanced similarity search for this article.